Bericote – Coventry

Bericote Properties

Project Summary

Burrows Graham were appointed by Bericote to undertake civil and structural engineering design services for three distribution warehouses on a 42-acre site in Coventry, with combined floor area of 780,000 sq ft. The development was construction by Glencar Construction and was completed in August 2022. Works started on site with the demolition of the former Toys R Us unit in October 2021 followed by the main development works with a 41 week overall programme.

Key Engineering Challenges

  • Flood mitigation measures former adjacent to the watercourse
  • Diversion of an existing Severn Trent Water Foul Water rising main
Project Name: Coventry Logistics Park
Architect: Corstorphine & Wright
Contractor: Glencar
Size: 780,000 sq ft
Completion date: August 2022
Sector: Industrial & Logistics